OBPAS Implementation Guide
Section 1: Executive Summary
Overview of the Product
The computerised and automatic building permission system offered under the National Urban Stack(NUS) facilitates citizens who seek permission for construction of a building within any Urban Local Body with a transparent, speedy, hassle-free and user-friendly procedure. Online Building Permission System (OBPS) is one of the components of a smart city that has the capability of providing a single window for acquiring building permits, NOCs, and clearances from multiple agencies or departments. Keeping in mind the benefits associated with the product offered, the proposed system is about to be implemented in 500+ ULBs across the country in 15 states and Union Territories. (For details on product features refer to Section-2).
Implementation Methodology for OBPS
For the offered product, the implementation process can be divided into six major distinctive stages. Each stage has predefined entry and exit criteria, roles & responsibilities to assure objective monitoring and decision making for the overall success of the engagement. The whole implementation lifecycle is typical of 35-40 weeks keeping in mind the entry, and exit criteria defined at the beginning and end of each stage is met within the recommended time.
Stage Zero-program setup and onboarding is a pre-requisite for the initiative to kick-off and requires setup of the governance model, implementation Team and decision regarding other significant elements of the initiative like funding and procurement process.
Stage One of the initiative requires scoping of the initiative and deciding on the priorities for implementation by the state implementation Team.
In stage three, the state Team will work upon identifying and finding solutions to the significant gaps in the product offered w.r.t. to the needs of the state.
Configuration and customisation of the product offered in the primary objective of stage four. This involves working on various aspects of state-specific needs and incorporating them into the product suite offered.
In stage four and five, post doing UAT and including all the necessary feedback on the product, the roll-out of the product is done at the state level (Go Live) from a couple of ULBs to pan state coverage. (For details on the implementation plan refer to Section-3).
Manpower Requirement For Implementation
The whole implementation cycle requires a Team of individuals with specific skill sets to work very closely. The state implementation unit comprises individuals with Program management, business analysis, implementation engineering, software engineering, architecture (DCR Domain) and capacity building skills. Depending upon the phases of implementing the initiative is in, the amount of effort by each participant in the smaller units will vary. (For details on resource sizing and requirements refer to Section-5)
Budgetary Requirement For Implementation
Based on close deliberations with various stakeholders, it is recommended that the budgetary allocation for the implementation of the initiative should be around 3 crores to 3.8 crores1 for statewide implementation and Operation and Maintenance Cost (per Year )for the initiative will be approximately 1.35 crores to 2.0 crores2. The budget allocated needs to be utilised for human resources requirements primarily. The budgetary allocation is recommended as per the NICSI standards published on https://www.nicsi.com/ (Check Annexure 1 for NICSI standard rates). The estimation of the budget will increase or decrease based on the rates applicable to the resources required. (For details on budgetary allocation guidelines refer to Section 5).
Critical Success Factors For Implementation
1 Assuming NICSI standard rate cards and 20% range on the actual estimated cost
2 Assuming NICSI standard rate cards and 20% range on the actual estimated cost.
Section 2: Online Building Permission System(OBPS) Implementation Methodology
This section provides an overview of the methodology for the state-wide implementation of OBPS. Implementation of OBPS is distributed across six distinct stages. Each stage has predefined entry and exit criteria, roles & responsibilities to assure objective monitoring and decision making for the overall success of the engagement. Details of each stage are defined in this section.
OBPS implementation program is expected to be completed within approximately 37 weeks with the resource deployment by the State and System Integrator(SI) Team (as defined below). However, it is critical that activities and exit criteria set for each stage are achieved to adhere to this timeline.
Six Stages of Implementation
Stage 0 - Program Setup/Onboarding
Set of initial critical activities that are undertaken on receiving a Letter of Enrollment from the state. Successful completion of these activities assures that the program is started with crucial personnel, System Integrator(SI) Teams and funds.
Stage 0 - Program Setup/ On-Boarding
Entry Criteria
Acceptance Letter sent by State
Exit Criteria
State Program Head/Nodal Officer Appointed
Identify funding for the program
Define State-specific procurement process
System Integrator(SI) Team Onboarding
Stage 1 - Program Kick-Off
This stage envisages the in-person interaction of crucial State officials and implementation System Integrator(SI) Teams to kick-start the program. This stage may require multiple interactions/meetings with different interest groups. The principal objective of these interactions is to identify Pilot ULBs, create an active collaboration & Governance approach and agree on a high-level timeline for the engagement.
Stage 1 - Program kick-off
Entry Criteria
Program setup is complete
Key Activities
Identify & agree on high-level scope and exclusions
Identify pilot ULBs
Project kick-off meeting and stakeholders consultation
Product Walkthroughs
Define Project Steering Committee structure and Project Governance process
Define phases of deployment
Agreement on Deployment Priorities and high-level delivery timelines
Exit Criteria
Implementation plan agreement with priority applications and broad timelines
Master data collection kickoff from Pilot ULBs
Implementation Team formed and appointed
Cloud Infrastructure procured
Project Office Space allocated
Capture State-specific processes
Stage 2 - Solution Design
During the Solution design stage key state officials and members, who are subject matter experts, are expected to share state by-laws and also help interpret these laws for the System Integrator(SI) Team. This stage baselines the State-specific product features in the Product Configuration report.
Stage 2 - Solution Design
Entry Criteria
State by-laws and scope available to Implementation Team
Key Activities
Templatization of DCR Rules
Validation of Templatization
Pre-UAT workshop to define product configuration
Initiate collection of master data from pilot ULBs
Solutioning approach for identified gaps
Optional: Define uniform by-laws across ULBs. May require a Business Process Re- engineering effort
Exit Criteria
By-laws available in a required format and reviewed by state Team
Product Configuration Report Sign Off
Solution agreement for required state-specific customisations
Stage 3 - Configuration & Customization
Configuration & customisation stage, spread across 12 weeks, envisages configuration of the product as per the baselined Product Configuration report and identified state-specific customisations. Active involvement of domain experts from the state Team is required in this stage to validate the implementation of state by-laws.
Stage 3 – Configuration & Customization
Entry Criteria
Product Configuration Report has been Signed Off by the State
Customisation and solution approach agreement with State Team
Key Activities
Setting up development environments
Customisation & configuration of DCR Rules
Customisation of BPA Workflow
Customisation of fee calculation
Development/customisation of reports and dashboards
Development/Integration of portal
Third-Party Integrations (NOC, Payment gateway, Digital signature)
Validation of DCR Rules
Updation of user manuals and other key documents
Preparation & execution of Test Cases
Setup support & maintenance processes & tools
Exit Criteria
Configured/Customized product that is fit for use by the State
Stage 4 - UAT & Go Live
During this stage, the active involvement of Pilot ULB officials is expected for thorough testing of the configured product. Training of the key ULB officials will also be undertaken during this stage, along with the promotion of the solution. The establishment of the State support Team and required processes are initiated in this stage.
Stage 4 – UAT & Go Live
Entry Criteria
Configured/Customized product ready to be deployed
Pilot ULBs available for UAT & Training
Key Activities
UAT Env Setup
UAT Testing
Issues/bug resolution
UAT Sign off from Pilot ULBs
Setting up the Production environment
Setting up Support Center & processes (Help Desk)
Training (Architects, Users, trainer)
Training the Support Resources
Marketing & promotion activities
Go Live & launch event
Exit Criteria
UAT Sign-off & Go Live for Pilot ULBs
Stage 5 – Rollout
On successful rollout in the Pilot ULBs, the solution will be rolled out to the rest of the ULBs in batches. Guidance and support from the State Team will be required to create the rollout plans and assure the necessary infrastructure for training and deployment is available at each ULB.
Note: The rollout phase needs to be detailed out for iterative activities of onboarding ULBs in batches.
Stage 5 – Rollout
Entry Criteria
Product/solution has been configured as per the baselined fitment study report, and the same has been tested by Key state members
Key Activities
ULB configurations
Logistics planning for training
Training the Architects/Users at the district level
Roll Out - All Locations
Stabilise product
Exit Criteria
Statewide Rollout in batches (of approximately 30 ULBs each)
Section 3: Roles and Responsibilities – OBPS Cell, NUS Team & System Integrator(SI)Team
This section outlines the activities involved in each stage of the implementation along with the responsibility and accountability of critical stakeholders - State, NUS Team and Implementation Team onboard.
OBPS Cell: OBPS Cell is the government-appointed body chaired by the Principal Secretary/Secretary, Urban Development Department with members from the Town and Country Planning Organization, Urban Development Department etc.
NUS Team: NUS Team is the National Program Management Unit established in Delhi which will provide all necessary support to the state concerning the implementation, Program Designing etc.
System Integrator (SI)Team: SI Team will be responsible for the rollout of the initiative in the state, providing all end to end support to the state w.r.t. The implementation of the products in the ULBs.
Execute - One who owns the accountability to complete the activity
Consult - One who may initiate, guide and in the process, handhold the execution of the activity
Task/Activity
NUS Team
OBPS Cell
SI Team
Stage 0 - Program Setup/ On-Boarding
Appoint State Program Head/Nodal Officer
Consult
Execute
Identify funding for the program
Consult
Execute
Define State-specific procurement process
Consult
Execute
System Integrator(SI) Team Onboarding
Consult
Execute
Provide the state-specific resource and infrastructure requirements
Execute
Consult
Stage 1 - Program kick-off
Identify & agree on high-level scope and exclusions
Consult
Consult
Execute
Identify Pilot ULBs
Execute
Consult
Project kick-off meeting and stakeholders consultation
Consult
Consult
Execute
Product Walkthroughs
Consult
Execute
Define Project Steering Committee structure and Project Governance process
Execute
Consult
Identify Key Team Members from State/Client End for
DCR Plan Scrutiny
BPA Workflow Process and Standards
Infra requirements procurement
Project Management
Execute
Execute
Agreement on Deployment Priorities and high-level delivery timelines
Execute
Execute
Appoint Data collection Team and arrange for data collection asks for Pilot ULBs
Execute
Consult
Implementation of Team formation and appointment
Execute
Consult
Cloud Infrastructure procurement
Execute
Consult
Project Office Space allocation
Execute
Consult
Capture State-specific processes
Consult
Execute
Set-up Project Management processes
Communication
Escalations & Risk management
Status reporting
Execute
Execute
Identify the Team Members for the Project
Execute
Consult
Attend the Kick-Off Meeting
Execute
Consult
Depute Full-Time Team Members for
DCR Plan Scrutiny
BPA Workflow Process and Standards
Infra requirements procurement
Project Management
Execute
Consult
Provide inputs for the Detailed Scope and Requirements
Execute
Consult
Initiate the Procurement Process for the Infra
Execute
Consult
Initiate System Integrator(SI) Team procurement
Execute
Consult
Initiate Program for Capacity Building
Execute
Consult
Initiate master data collection from pilot ULBs
Execute
Consult
Sign Off Project Charter
Execute
Consult
Stage 2 - Solution Design
Product Walkthroughs with subject matter experts (Urban Town Planners & Architects) and State implementation Team
Consult
Execute
Walkthrough on state by-laws, eDCR and product process flows.
Review DCRs captured in the template
Define OBPS feature implementation across phases/ULBs.
Provide process study questionnaires to identify product deviations
Define Artefacts to be collected during the study
Product documentation
Master Data templates
Execute (State bye-laws & EDCR)
Execute
Capture State-specific Product configuration requirements (if any) based on product walkthrough demos and discussions for Pilot ULBs
Consult
Execute
Coordinate and Organize Pre UAT Workshop with relevant stakeholders of identified Pilot ULBs
Execute
Execute
Preparation of Product Configuration Report
Consult
Execute
Capture state Bylaws into DCR template
Execute
Consult
Provide Test data (drawings to be uploaded)
Execute
Consult
Attend Product Demo and Offer required inputs
Execute
Consult
Validation of DCR Rules Templates
Execute
Consult
Participate in Pre UAT workshop and provide inputs for the Product configuration
Execute
Consult
Product Configuration Report Sign Off
Execute
Consult
Stage 3 – Configuration & Customization
Setting up development & UAT environments
Consult
Execute
Customization & configuration of DCR Rules
Consult
Execute
Customisation of BPA Workflow
Consult
Execute
Development of reports and dashboards
Consult
Execute
Development/Integration of portal
Consult
Execute
Third-Party Integrations (NOC, Payment gateway, Digital signature)
Consult
Execute
Validation of DCR Rules
Execute
Consult
Preparation & execution of Test Cases
Consult
Execute
Setup support & maintenance processes & tools
Consult
Execute
Provide clarification and guidance on the interpretation of state Bylaws
Execute
Consult
Test configured product and provide feedback
Execute
Consult
Provide support in integrating Third-Party State services/departments
Execute
Consult
Test product features and provides feedback
Execute
Consult
Support System Integrator(SI) Team in integration with Third-party solutions
Execute
Consult
Stage 4 – UAT & Go Live
Readiness Checklist
Consult
Execute
UAT guidelines
Consult
Execute
Pilot checklist
Consult
Execute
Marketing and public outreach strategies
Consult
Execute
Provide Training for Pilot ULBs (Architects, Users & trainers)
Consult
Execute
Provide User manuals and help documents
Consult
Execute
Getting Product Ready for UAT
Infra configurations and UAT deployment Master Data Finalization
Employee Data Finalization
Consult
Execute
Setting up support processes
Consult
Execute
Master Data uploads
Consult
Execute
Legacy data (if applicable) capture
Consult
Execute
UAT Support
Consult
Execute
Preparation/update User Manuals to make it relevant for State
Consult
Execute
Making the Pilot ULBs live
Consult
Execute
Testing and signoff
Execute
Consult
Identify and share issues & help analyse issues/defects
Execute
Consult
Deployment of Support Resources
Execute
Consult
Provision of Training Facility
Execute
Consult
Setting up of Support Center/Help Desk
Execute
Consult
Communicate with NOC Departments
Execute
Consult
Readiness assessment
Execute
Consult
Coordinate with Pilot ULBs to ensure public outreach
Execute
Consult
Ensure the announcement of the Pilot launch
Execute
Consult
Setting up a help desk to handhold ULBs undergoing Pilot
Execute
Consult
Setting up a review process to review the health of the Pilot launch for 2-3 weeks
Execute
Consult
Stage 5: Rollout
Training the Architects (District Level)
Consult
Execute
Training the State/Client Users (District Level)
Consult
Execute
Stabilisation Period Support with On Field Support
Consult
Execute
Statewide Rollout
Execute
Execute
Operations and Support
Execute
Execute
Product Support
Execute
Execute
Provision of Training Facility at Districts
Execute
Consult
Program Management of Training
Execute
Consult
Program Management of Client/User Infra
Execute
Consult
Program Management of Rollout
Execute
Consult
Section 4- Resource, effort estimation and Budget Requirements for the Program
Implementation effort and Budget requirements of the program(Stage 1 to Stage 5)
Implementation Effort/Cost Summary (Stage 1 to Stage 5) (In Man-Months)
Type of Resources
Effort(in Man-Months)
Total Cost(in Cr)
Program Management
Project Director
Program Manager
Project Manager
18
0.668
Configuration and Customization
Business Analyst
Cloud Engineer
Software
Engineer
63
1.658
UAT and Go Live support
Support Engineer
IEC Consultant
20
0.36
Capacity Building
Consultant
3
0.108
Help Desk
Helpdesk Support
15
0.09
District Level Support
Business Analyst
Support Engineer
Consultant
23
0.533
Total
142
3.417
Implementation Budget requirements of the program
Operations and Maintenance Cost Summary per year(in Cr)
Type of Resources
Total Budget Required(in Cr)
Program Management
Project Manager
0.432
Application Support
Business Analyst/ Support Engineer
0.84
Help Desk
Helpdesk Support
0.144
Hosting Infrastructure
0.28
Total
1.69
The summary of the budgeting is as per the NICSI rates(Please refer to annexure-1) and assuming a 20% range.
One time Cost for Statewide Implementation (Stage 1- Stage 5)
3.0 Cr – 3.8 Cr
Recurring Cost (YoY)-(Operating and Maintenance Cost)
1.35 Cr – 2.0 Cr
Note: Overall Budget Summary (in INR) is as per NICSI rates
Resource requirements for the OBPS cell required to be formed by the state
Resource Name
No. Of Resources
Project Sponsor
1
Plan Process Expert
2
Nodal Officer
1
Development Control Rules (DCR) Expert
2
Note: Designation mentioned above are as per designations known driving OBPS implementation at the state level as explained below
Project Sponsor: Is the Head of the OBPS Cell who will drive the project from the State Side
Plan Process Expert: The two resources that will provide the BPA application process and workflow. Validate the UAT in compliance with the expected outcome.
Development Control Rules Experts: they should have the domain skills on the drawings and plan along with the DCR rules of the State. They would provide the templatization of the DCR Rules, validate the same once configured in the Application and approve.
Nodal Officer: He would play the organise role who will provide all logistics support and scheduling of activities related to the project, Rollout and training of both Engineers and ULB officials across the State.
Last updated