OBPAS Implementation Guide

Section 1: Executive Summary

Overview of the Product

The computerised and automatic building permission system offered under the National Urban Stack(NUS) facilitates citizens who seek permission for construction of a building within any Urban Local Body with a transparent, speedy, hassle-free and user-friendly procedure. Online Building Permission System (OBPS) is one of the components of a smart city that has the capability of providing a single window for acquiring building permits, NOCs, and clearances from multiple agencies or departments. Keeping in mind the benefits associated with the product offered, the proposed system is about to be implemented in 500+ ULBs across the country in 15 states and Union Territories. (For details on product features refer to Section-2).

Implementation Methodology for OBPS

For the offered product, the implementation process can be divided into six major distinctive stages. Each stage has predefined entry and exit criteria, roles & responsibilities to assure objective monitoring and decision making for the overall success of the engagement. The whole implementation lifecycle is typical of 35-40 weeks keeping in mind the entry, and exit criteria defined at the beginning and end of each stage is met within the recommended time.

Stage Zero-program setup and onboarding is a pre-requisite for the initiative to kick-off and requires setup of the governance model, implementation Team and decision regarding other significant elements of the initiative like funding and procurement process.

Stage One of the initiative requires scoping of the initiative and deciding on the priorities for implementation by the state implementation Team.

In stage three, the state Team will work upon identifying and finding solutions to the significant gaps in the product offered w.r.t. to the needs of the state.

Configuration and customisation of the product offered in the primary objective of stage four. This involves working on various aspects of state-specific needs and incorporating them into the product suite offered.

In stage four and five, post doing UAT and including all the necessary feedback on the product, the roll-out of the product is done at the state level (Go Live) from a couple of ULBs to pan state coverage. (For details on the implementation plan refer to Section-3).

Manpower Requirement For Implementation

The whole implementation cycle requires a Team of individuals with specific skill sets to work very closely. The state implementation unit comprises individuals with Program management, business analysis, implementation engineering, software engineering, architecture (DCR Domain) and capacity building skills. Depending upon the phases of implementing the initiative is in, the amount of effort by each participant in the smaller units will vary. (For details on resource sizing and requirements refer to Section-5)

Budgetary Requirement For Implementation

Based on close deliberations with various stakeholders, it is recommended that the budgetary allocation for the implementation of the initiative should be around 3 crores to 3.8 crores1 for statewide implementation and Operation and Maintenance Cost (per Year )for the initiative will be approximately 1.35 crores to 2.0 crores2. The budget allocated needs to be utilised for human resources requirements primarily. The budgetary allocation is recommended as per the NICSI standards published on https://www.nicsi.com/ (Check Annexure 1 for NICSI standard rates). The estimation of the budget will increase or decrease based on the rates applicable to the resources required. (For details on budgetary allocation guidelines refer to Section 5).

Critical Success Factors For Implementation

1 Assuming NICSI standard rate cards and 20% range on the actual estimated cost

2 Assuming NICSI standard rate cards and 20% range on the actual estimated cost.

Section 2: Online Building Permission System(OBPS) Implementation Methodology

This section provides an overview of the methodology for the state-wide implementation of OBPS. Implementation of OBPS is distributed across six distinct stages. Each stage has predefined entry and exit criteria, roles & responsibilities to assure objective monitoring and decision making for the overall success of the engagement. Details of each stage are defined in this section.

OBPS implementation program is expected to be completed within approximately 37 weeks with the resource deployment by the State and System Integrator(SI) Team (as defined below). However, it is critical that activities and exit criteria set for each stage are achieved to adhere to this timeline.

Six Stages of Implementation

Stage 0 - Program Setup/Onboarding

Set of initial critical activities that are undertaken on receiving a Letter of Enrollment from the state. Successful completion of these activities assures that the program is started with crucial personnel, System Integrator(SI) Teams and funds.

Stage 0 - Program Setup/ On-Boarding

Entry Criteria

Acceptance Letter sent by State

Exit Criteria

  • State Program Head/Nodal Officer Appointed

  • Identify funding for the program

  • Define State-specific procurement process

  • System Integrator(SI) Team Onboarding

Stage 1 - Program Kick-Off

This stage envisages the in-person interaction of crucial State officials and implementation System Integrator(SI) Teams to kick-start the program. This stage may require multiple interactions/meetings with different interest groups. The principal objective of these interactions is to identify Pilot ULBs, create an active collaboration & Governance approach and agree on a high-level timeline for the engagement.

Stage 1 - Program kick-off

Entry Criteria

Program setup is complete

Key Activities

  • Identify & agree on high-level scope and exclusions

  • Identify pilot ULBs

  • Project kick-off meeting and stakeholders consultation

  • Product Walkthroughs

  • Define Project Steering Committee structure and Project Governance process

  • Define phases of deployment

  • Agreement on Deployment Priorities and high-level delivery timelines

Exit Criteria

  • Implementation plan agreement with priority applications and broad timelines

  • Master data collection kickoff from Pilot ULBs

  • Implementation Team formed and appointed

  • Cloud Infrastructure procured

  • Project Office Space allocated

  • Capture State-specific processes

Stage 2 - Solution Design

During the Solution design stage key state officials and members, who are subject matter experts, are expected to share state by-laws and also help interpret these laws for the System Integrator(SI) Team. This stage baselines the State-specific product features in the Product Configuration report.

Stage 2 - Solution Design

Entry Criteria

State by-laws and scope available to Implementation Team

Key Activities

  • Templatization of DCR Rules

  • Validation of Templatization

  • Pre-UAT workshop to define product configuration

  • Initiate collection of master data from pilot ULBs

  • Solutioning approach for identified gaps

  • Optional: Define uniform by-laws across ULBs. May require a Business Process Re- engineering effort

Exit Criteria

  • By-laws available in a required format and reviewed by state Team

  • Product Configuration Report Sign Off

  • Solution agreement for required state-specific customisations

Stage 3 - Configuration & Customization

Configuration & customisation stage, spread across 12 weeks, envisages configuration of the product as per the baselined Product Configuration report and identified state-specific customisations. Active involvement of domain experts from the state Team is required in this stage to validate the implementation of state by-laws.

Stage 3 – Configuration & Customization

Entry Criteria

  • Product Configuration Report has been Signed Off by the State

  • Customisation and solution approach agreement with State Team

Key Activities

  • Setting up development environments

  • Customisation & configuration of DCR Rules

  • Customisation of BPA Workflow

  • Customisation of fee calculation

  • Development/customisation of reports and dashboards

  • Development/Integration of portal

  • Third-Party Integrations (NOC, Payment gateway, Digital signature)

  • Validation of DCR Rules

  • Updation of user manuals and other key documents

  • Preparation & execution of Test Cases

  • Setup support & maintenance processes & tools

Exit Criteria

Configured/Customized product that is fit for use by the State

Stage 4 - UAT & Go Live

During this stage, the active involvement of Pilot ULB officials is expected for thorough testing of the configured product. Training of the key ULB officials will also be undertaken during this stage, along with the promotion of the solution. The establishment of the State support Team and required processes are initiated in this stage.

Stage 4 – UAT & Go Live

Entry Criteria

  • Configured/Customized product ready to be deployed

  • Pilot ULBs available for UAT & Training

Key Activities

  • UAT Env Setup

  • UAT Testing

  • Issues/bug resolution

  • UAT Sign off from Pilot ULBs

  • Setting up the Production environment

  • Setting up Support Center & processes (Help Desk)

  • Training (Architects, Users, trainer)

  • Training the Support Resources

  • Marketing & promotion activities

  • Go Live & launch event

Exit Criteria

UAT Sign-off & Go Live for Pilot ULBs

Stage 5 – Rollout

On successful rollout in the Pilot ULBs, the solution will be rolled out to the rest of the ULBs in batches. Guidance and support from the State Team will be required to create the rollout plans and assure the necessary infrastructure for training and deployment is available at each ULB.

Note: The rollout phase needs to be detailed out for iterative activities of onboarding ULBs in batches.

Stage 5 – Rollout

Entry Criteria

Product/solution has been configured as per the baselined fitment study report, and the same has been tested by Key state members

Key Activities

  • ULB configurations

  • Logistics planning for training

  • Training the Architects/Users at the district level

  • Roll Out - All Locations

  • Stabilise product

Exit Criteria

Statewide Rollout in batches (of approximately 30 ULBs each)

Section 3: Roles and Responsibilities – OBPS Cell, NUS Team & System Integrator(SI)Team

This section outlines the activities involved in each stage of the implementation along with the responsibility and accountability of critical stakeholders - State, NUS Team and Implementation Team onboard.

OBPS Cell: OBPS Cell is the government-appointed body chaired by the Principal Secretary/Secretary, Urban Development Department with members from the Town and Country Planning Organization, Urban Development Department etc.

NUS Team: NUS Team is the National Program Management Unit established in Delhi which will provide all necessary support to the state concerning the implementation, Program Designing etc.

System Integrator (SI)Team: SI Team will be responsible for the rollout of the initiative in the state, providing all end to end support to the state w.r.t. The implementation of the products in the ULBs.

Execute - One who owns the accountability to complete the activity

Consult - One who may initiate, guide and in the process, handhold the execution of the activity

Task/ActivityNUS TeamOBPS CellSI Team

Stage 0 - Program Setup/ On-Boarding

Appoint State Program Head/Nodal Officer

Consult

Execute

Identify funding for the program

Consult

Execute

Define State-specific procurement process

Consult

Execute

System Integrator(SI) Team Onboarding

Consult

Execute

Provide the state-specific resource and infrastructure requirements

Execute

Consult

Stage 1 - Program kick-off

Identify & agree on high-level scope and exclusions

Consult

Consult

Execute

Identify Pilot ULBs

Execute

Consult

Project kick-off meeting and stakeholders consultation

Consult

Consult

Execute

Product Walkthroughs

Consult

Execute

Define Project Steering Committee structure and Project Governance process

Execute

Consult

Identify Key Team Members from State/Client End for

  • DCR Plan Scrutiny

  • BPA Workflow Process and Standards

  • Infra requirements procurement

  • Project Management

Execute

Execute

Agreement on Deployment Priorities and high-level delivery timelines

Execute

Execute

Appoint Data collection Team and arrange for data collection asks for Pilot ULBs

Execute

Consult

Implementation of Team formation and appointment

Execute

Consult

Cloud Infrastructure procurement

Execute

Consult

Project Office Space allocation

Execute

Consult

Capture State-specific processes

Consult

Execute

Set-up Project Management processes

  • Communication

  • Escalations & Risk management

  • Status reporting

Execute

Execute

Identify the Team Members for the Project

Execute

Consult

Attend the Kick-Off Meeting

Execute

Consult

Depute Full-Time Team Members for

  • DCR Plan Scrutiny

  • BPA Workflow Process and Standards

  • Infra requirements procurement

  • Project Management

Execute

Consult

Provide inputs for the Detailed Scope and Requirements

Execute

Consult

Initiate the Procurement Process for the Infra

Execute

Consult

Initiate System Integrator(SI) Team procurement

Execute

Consult

Initiate Program for Capacity Building

Execute

Consult

Initiate master data collection from pilot ULBs

Execute

Consult

Sign Off Project Charter

Execute

Consult

Stage 2 - Solution Design

Product Walkthroughs with subject matter experts (Urban Town Planners & Architects) and State implementation Team

Consult

Execute

Walkthrough on state by-laws, eDCR and product process flows.

  1. Review DCRs captured in the template

  2. Define OBPS feature implementation across phases/ULBs.

  3. Provide process study questionnaires to identify product deviations

  4. Define Artefacts to be collected during the study

  5. Product documentation

  6. Master Data templates

Execute (State bye-laws & EDCR)

Execute

Capture State-specific Product configuration requirements (if any) based on product walkthrough demos and discussions for Pilot ULBs

Consult

Execute

Coordinate and Organize Pre UAT Workshop with relevant stakeholders of identified Pilot ULBs

Execute

Execute

Preparation of Product Configuration Report

Consult

Execute

Capture state Bylaws into DCR template

Execute

Consult

Provide Test data (drawings to be uploaded)

Execute

Consult

Attend Product Demo and Offer required inputs

Execute

Consult

Validation of DCR Rules Templates

Execute

Consult

Participate in Pre UAT workshop and provide inputs for the Product configuration

Execute

Consult

Product Configuration Report Sign Off

Execute

Consult

Stage 3 – Configuration & Customization

Setting up development & UAT environments

Consult

Execute

Customization & configuration of DCR Rules

Consult

Execute

Customisation of BPA Workflow

Consult

Execute

Development of reports and dashboards

Consult

Execute

Development/Integration of portal

Consult

Execute

Third-Party Integrations (NOC, Payment gateway, Digital signature)

Consult

Execute

Validation of DCR Rules

Execute

Consult

Preparation & execution of Test Cases

Consult

Execute

Setup support & maintenance processes & tools

Consult

Execute

Provide clarification and guidance on the interpretation of state Bylaws

Execute

Consult

Test configured product and provide feedback

Execute

Consult

Provide support in integrating Third-Party State services/departments

Execute

Consult

Test product features and provides feedback

Execute

Consult

Support System Integrator(SI) Team in integration with Third-party solutions

Execute

Consult

Stage 4 – UAT & Go Live

Readiness Checklist

Consult

Execute

UAT guidelines

Consult

Execute

Pilot checklist

Consult

Execute

Marketing and public outreach strategies

Consult

Execute

Provide Training for Pilot ULBs (Architects, Users & trainers)

Consult

Execute

Provide User manuals and help documents

Consult

Execute

Getting Product Ready for UAT

Infra configurations and UAT deployment Master Data Finalization

Employee Data Finalization

Consult

Execute

Setting up support processes

Consult

Execute

Master Data uploads

Consult

Execute

Legacy data (if applicable) capture

Consult

Execute

UAT Support

Consult

Execute

Preparation/update User Manuals to make it relevant for State

Consult

Execute

Making the Pilot ULBs live

Consult

Execute

Testing and signoff

Execute

Consult

Identify and share issues & help analyse issues/defects

Execute

Consult

Deployment of Support Resources

Execute

Consult

Provision of Training Facility

Execute

Consult

Setting up of Support Center/Help Desk

Execute

Consult

Communicate with NOC Departments

Execute

Consult

Readiness assessment

Execute

Consult

Coordinate with Pilot ULBs to ensure public outreach

Execute

Consult

Ensure the announcement of the Pilot launch

Execute

Consult

Setting up a help desk to handhold ULBs undergoing Pilot

Execute

Consult

Setting up a review process to review the health of the Pilot launch for 2-3 weeks

Execute

Consult

Stage 5: Rollout

Training the Architects (District Level)

Consult

Execute

Training the State/Client Users (District Level)

Consult

Execute

Stabilisation Period Support with On Field Support

Consult

Execute

Statewide Rollout

Execute

Execute

Operations and Support

Execute

Execute

Product Support

Execute

Execute

Provision of Training Facility at Districts

Execute

Consult

Program Management of Training

Execute

Consult

Program Management of Client/User Infra

Execute

Consult

Program Management of Rollout

Execute

Consult

Section 4- Resource, effort estimation and Budget Requirements for the Program

Implementation effort and Budget requirements of the program(Stage 1 to Stage 5)

Implementation Effort/Cost Summary (Stage 1 to Stage 5) (In Man-Months)

Type of Resources

Effort(in Man-Months)

Total Cost(in Cr)

Program Management

  1. Project Director

  2. Program Manager

  3. Project Manager

18

0.668

Configuration and Customization

  1. Business Analyst

  2. Cloud Engineer

  3. Software

  4. Engineer

63

1.658

UAT and Go Live support

  1. Support Engineer

  2. IEC Consultant

20

0.36

Capacity Building

  1. Consultant

3

0.108

Help Desk

  1. Helpdesk Support

15

0.09

District Level Support

  1. Business Analyst

  2. Support Engineer

  3. Consultant

23

0.533

Total

142

3.417

Implementation Budget requirements of the program

Operations and Maintenance Cost Summary per year(in Cr)

Type of Resources

Total Budget Required(in Cr)

Program Management

Project Manager

0.432

Application Support

Business Analyst/ Support Engineer

0.84

Help Desk

Helpdesk Support

0.144

Hosting Infrastructure

0.28

Total

1.69

The summary of the budgeting is as per the NICSI rates(Please refer to annexure-1) and assuming a 20% range.

One time Cost for Statewide Implementation (Stage 1- Stage 5)3.0 Cr – 3.8 Cr

Recurring Cost (YoY)-(Operating and Maintenance Cost)

1.35 Cr – 2.0 Cr

Note: Overall Budget Summary (in INR) is as per NICSI rates

Resource requirements for the OBPS cell required to be formed by the state

Resource NameNo. Of Resources

Project Sponsor

1

Plan Process Expert

2

Nodal Officer

1

Development Control Rules (DCR) Expert

2

Note: Designation mentioned above are as per designations known driving OBPS implementation at the state level as explained below

Project Sponsor: Is the Head of the OBPS Cell who will drive the project from the State Side

Plan Process Expert: The two resources that will provide the BPA application process and workflow. Validate the UAT in compliance with the expected outcome.

Development Control Rules Experts: they should have the domain skills on the drawings and plan along with the DCR rules of the State. They would provide the templatization of the DCR Rules, validate the same once configured in the Application and approve.

Nodal Officer: He would play the organise role who will provide all logistics support and scheduling of activities related to the project, Rollout and training of both Engineers and ULB officials across the State.